PORT CONCESSIONS ON FUTURE LANDS: WHAT HAPPENS IF THE ADMINISTRATION EXCEEDS THE TWO-YEAR LIMIT?

1.- Initial term port concessions.

A well-known practice in the state port sector and permitted by law (Art. 81.3 of Royal Legislative Decree 2/2011, of September 5, Consolidated Text of the Law of State Ports and the Merchant Marine, TRLPEMM) consists of the Port Authority granting a concession on land and water that it cannot yet make available to the new concessionaire.

The law stipulates: a) that the land and water in question are already under concession to a third party at the time of the concession’s granting (a concession whose expiration date must be imminent); and b) that the concession involves cases where the Port Authority must carry out works prior to making the concession available. The start of the new concession term must coincide with the expiration of the existing concession or with the completion of the works by the Port Authority. This provision is included in Rule 4 of the general terms and conditions for granting concessions in the state port public domain, approved by Order FOM/938 of March 27.

Although these portfolio concessions are not the general rule, they can constitute a useful instrument for public port management subject to profitability and efficiency criteria (art. 66.3 TRLPEMM), which must take advantage of all opportunities to attract traffic in a constantly evolving market.

It is not a blank check: the law clearly states that no more than two years may elapse from the agreement to grant the concession until the effective delivery of the land .

We wonder what happens if the Administration cannot meet that time limit.

2.- Cases of non-compliance by the Port Authority.

We will distinguish three possibilities:

  1. Something that can happen, and unfortunately is not uncommon, is that the execution of public works projects extends beyond the contractual deadline. In our case, the complexity of maritime works is well known. In this regard, although the regime established in Law 9/2017, of November 8, on Public Sector Contracts, regarding the effects, performance, and termination of administrative contracts, does not apply to contracts of Port Authorities, which are private-law contracts (Art. 24.2 Royal Decree 2/2011), these contracts will undoubtedly include a specific execution regime, with extensions, penalties, and contract termination.
  2. It is also possible that the planning foreseen by the Port Authority for the tendering and execution of its works will not be fulfilled or will need to be modified.
  3. We believe, however, that it should be difficult for the existing concession to not have ended on its scheduled date. For example, we think it would be unusual for the Port Authority, having granted a concession for the land and waters of another existing concession nearing its expiration, to choose to extend it. It is also possible that there might be a dispute regarding the expiration date of the existing concession, but it seems logical that, in such a case, this issue would have arisen at the time the new concession was granted, leading to an appeal by the original concession holder.

3. Premises for analyzing the possible consequences.

Given the legal complexity and highly case-specific nature of this issue, our objective is not to find a magic bullet or a one-size-fits-all solution, but rather to establish legal premises that can serve as a basis for a subsequent in-depth analysis of the cases that may arise. Leaving aside other possible approaches, we believe that a reasonable starting point could be the following:

  1. It can be understood that the concession has been validly granted . A separate issue is that its full effectiveness is delayed until the land and water it covers are made available/the pre-existing concession is terminated.
  2. Failure to comply with the two-year limit does not entail any automatic legal consequence of a resolutory or extinctive nature in art.81.3 , nor is it a cause of extinction under art.96. The law does not say that in case of non-compliance with the two-year term the granting necessarily loses all validity, nor that the concession is extinguished or that it must necessarily be extinguished.
  3. But the concession does not remain in a legal limbo .
    1. It could be interpreted that there is a case of review of the conditions of the concession – ex officio or at the request of the party – of art.89 TRLPEMM, with what this may imply (among other things, the possibility of maintaining the concession under other conditions and the possibility of extinguishing it).
    1. It could also be interpreted, although it seems more debatable in principle, that the concessionaire could have the right to waive the concession without loss of the bond because he is in a situation similar to that of Rule 11 PCG.
  4. All this is apart from the possibility, which cannot be ruled out a priori, that the concessionaire may claim from the Administration the damages caused by the breach.

It is obvious that different approaches are possible. But we believe that the one we propose has the advantage of focusing on the new concession and leaving open a wide range of possibilities.

Román Eguinoa de San Román